Local LERT Mercy work, South St. Louis Flood update

Start

Calendar
May 20, 2023
Time
12:00am CT

End

Calendar
May 27, 2023
Time
4:00pm CT

Description

All damaged drywall and wet insulation has been removed from the flooded basement. Currently we have 5 fans drying the concrete walls and studs. Next Saturday May 27th we will install new insulation and hang 22 sheets of drywall. We will also place the first coat of tape and mud. The homeowner and his grandsons will conduct the second and third coats of mud and do all final sanding. Therefore we will only need to deploy one more saturday at this location. Any questions, please contact Kris Schuldt pitchatent@centurytel.net or text to 314-971-5747.